The resurfacing contractor, Rack & Ballauer, will be resurfacing Hopewell Road next week, starting Monday, Aug. 26.

The resurfacing work is weather dependent.  If it rains, work on the roadway will shift to the week of Sept. 2.

Access will be maintained to the Montgomery Safety Center, Twin Lakes north campus, and residential driveways. There may be short windows of time when they are milling or resurfacing directly in front of the access.

Flaggers will maintain traffic on Hopewell Road.  Cars will be allowed to pass in one direction at a time while they are working in the other lane.

Expect traffic delays.  They are permitted to work from 8:30 a.m. to 3:30 p.m. to avoid disruption to the morning and evening rush hour.

On Monday and Tuesday, Aug. 27, the contractor will be milling off the existing asphalt surface. On Wednesday, Aug. 28, they will be doing pavement repairs. Towards the end of the week, they will be resurfacing the roadway.  The pavement will be going down in two layers.