The Montgomery Quarter (formerly known as the Gateway Redevelopment Area (GRA)), located along the east side of Montgomery Road between Ronald Reagan Cross County Highway and Main Street, has been a priority for the City for many years. A vision for this site was first documented in the 2006-2011 Strategic Plan.

The concept of expanding the redevelopment area to include the land just east of Montgomery Road at the end of Ronald Reagan Cross County Highway originated and evolved from the process to select a development team in 2015. From that point, the City has worked diligently with a multitude of partners on engineering studies and design to determine the roadway modifications required to allow redevelopment of the additional land.

The intersection improvement project will improve traffic patterns at the existing interchange and provide better access to the Montgomery Quarter. Key project partners throughout the process include the Ohio-Kentucky-Indiana Regional Council of Governments (OKI); Hamilton County Commissioners, Engineer’s Office, and Transportation Improvement District (TID); Ohio Department of Transportation (ODOT); Sycamore Community Schools; State legislators; and the Montgomery City Council and Chamber of Commerce.

For more information on the Montgomery Quarter roundabout, visit montgomeryohio.org/montgomery-quarter-roundabout-information.  Contact Public Works Director Gary Heitkamp at gheitkamp@montgomeryohio.org or 513-792-8321 with any additional questions.
 

Below is a timeline showing critical milestones during the development of the roundabout project.

 

Critical MilestoneDate
GRA Open HouseNovember 2014
Concept to Expand the GRA Site September 2015
Traffic Analysis and Alternatives EvaluationDecember 2015
Preferred Alternative IdentifiedJanuary 2016
Interchange Operations Study ApprovedSeptember 2016
OKI Awards Surface Transportation Program GrantOctober 2016
Hamilton County TID Grant AwardJanuary 2017
Project Design BeginsMay 2017
Roundabout Open House #1May 2018
Technical Peer Review of Roundabout DesignJune 2018
Hamilton County TID Grant AwardAugust 2018
Roundabout Open House #2January 2019
OKI Transportation Improvement Program GrantJanuary 2019
Presentation to OKI Board of DirectorsMarch 2019
Presentation to Hamilton County TID BoardMarch 2019
Hamilton County Awards Municipal Road Fund GrantMay 2019
Project Design CompleteAugust 2019
Anticipated Award of Construction ContractDecember 2019
Anticipated Start of ConstructionFebruary 2020
Anticipated End of ConstructionMarch 2021